Sample Snagging Survey Report, Liverpool
Customer Case Study & Sample Snagging Survey Report, 93 Kevins Drive, Kirby, Liverpool
Tuesday, 22 September 2020
“Very thorough and professional, would recommend and certainly work with again.”
The Report
LOCATION 1 93 ST KEVIN’S DRIVE KIRKBY L32 1BB
Assigned to Identification
The overall finish of the house is poor with little attention to detail, in particular, the decoration throughout is a poor standard and gives the house the feeling that it was rushed to completion. The extractor ducts and boiler flue require cavity trays installing to comply with NHBC Standards Chapter 6.1.17
LOCATION 2 FRONT ELEVATION
Assigned To Landscaper
The front bed needs planting.
LOCATION 3 FRONT ELEVATION
Assigned To Joiner
The front door cill needs an end cap fitting.
LOCATION 4 FRONT ELEVATION
Assigned To Groundworker
The gap both sides of the front door needs filling with limestone chippings.
LOCATION 5 FRONT ELEVATION
Assigned to Bricklayer
The timber needs removing from over the front door lintel.
View full report
Snagging Report
Tuesday, 22 September 2020
95 Issues Identified