Sample Snagging Survey Report, West Yorkshire
Customer Case Study & Sample Snagging Survey Report, Montague Close, Glusburn
Saturday, 15 August 2020
“Very thorough and professional, would recommend and certainly work with again.”
The Report
LOCATION 1 9 MONTAGUE CLOSE GLUSBURN BD20 8F
Assigned to Identification
The house has been completed to a reasonable standard, more attention to detail would have eliminated the majority of issues. The rear garden area is of concern, whilst appreciating that the newly laid turf has been extensively watered, it is impossible to walk on the turf without sinking into it. This would suggest either too much topsoil has been placed or the garden could require land drainage. This needs monitoring before a solution can be agreed upon.
Throughout the house there are areas of mould showing on the skirting boards, this would indicate excess moisture within the house.
LOCATION 2 FRONT ELEVATION
Assigned To Groundworker
The water stop tap lid needs lowering to allow a mower to pass over it.
LOCATION 3 FRONT ELEVATION
Assigned To Brick Cleaner
The stonework around the front windows need the mortor staining removing.
LOCATION 4 FRONT ELEVATION
Assigned To Roofer / Plumber
The pointing over the low level canopy appears to has sealant missing.
LOCATION 5 FRONT ELEVATION
Assigned to Electrican
The wires behind the bells push needs tidying.
View full report
Snagging Report
Saturday, 15 August 2020
94 Issues Identified